top of page

WHITE OAK'S LEISURE CENTRE.

Swimming Pool Preparation.
Completed in 2022 Complete Blasting Services supplied the surface preparation on the new White Oak's Leisure Centre in Reading.
Using a sharp R-Grit we applied a uniform profile to the newly poured concrete walls.
The purpose of this was to create a clean key for the new pool lining guaranteeing strong adherence.
using the Shotblasting method we are able to regulate the pressure to accurately profile the concretes flush finish.
Project Value £8,000


The Process.
*Grit blast the full internal swimming pool walls using R-grit.
*On completion provide a full clean out and waste disposal of all material leaving the site clean for the pool linings to proceed.
*Access and ventilation not required as the building at the time under construction was open sided.
*The works included 2 pools, The lane swimming large pool & a small children's pool.